News Flash

Projects

10 Stories
Posted on: November 13, 2020

Harvey Park Greenway Plan

SUNRISEHPGRAPHICpng

OCTOBER 2020 UPDATE: The first public meeting was held on 9/22/20 with positive response.  NEPA documents have been submitted to TDOT.  Once NEPA has been approved, the Design NTP should be issued and design can be finalized.  _...

Read on...

Additional Info... Projects
Posted on: November 5, 2020

Tom Lunn Road Improvement Project

Tom Lunn Road intersecting John Lunn Road

OCTOBER 2020 UPDATE: 

With the approval of funds for R.O.W. acquisition approved at the 10/19/20 BOMA meeting, the City will begin contacting property owners immediately beginning with the multi-tract holders. Project bid date is still planned for...

Read on...

Additional Info... Projects
Posted on: November 5, 2020

Buckner Lane Widening

Buckner Lane

OCTOBER 2020 UPDATE: Preliminary engineering for North Segment is progressing to 65% design. Considerable coordination underway with new residential developments along Buckner Lane corridor. Consultant team is ready to begin ROW acquisition proc...

Read on...

Additional Info... Projects
Posted on: November 5, 2020

Traffic Signals at Saturn Parkway exit ramps & Port Royal Road

Traffic Signal project at Saturn Parkway and Port Royal Road

OCTOBER 2020 UPDATE:

Initial signal timing adjustments partially complete while awaiting warranty repairs from TDOT contractor to complete initial settings; traffic counts completed; Technical Memo pending outlining equipment upgrades needed at each inters...

Read on...

See News Release For Details Projects
Posted on: November 13, 2020

Duplex Road (SR-247) Widening Project

DuplexRdSHGroup

OCTOBER 2020 UPDATE: Project is substantially complete. Ribbon Cutting was on 9/8/20. Per our requests, Eutaw will be working on a few drainage items including the modification of one driveway in the Newtown area and an existing drainage basin and flow pa...

Read on...

More information... Projects
Posted on: November 13, 2020

Buckner Road Widening and Gateway Corridor

Rendering of proposed Buckner Road widening and gateway corridor

OCTOBER 2020 UPDATE: Preliminary engineering for North Segment is progressing to 65% design. Considerable coordination underway with new residential developments along Buckner Lane corridor. Consultant team is ready to begin ROW acquisition process for No...

Read on...

Additional Info... Projects
Posted on: November 5, 2020

I-65 Interchange at Buckner Road Extension

I-65 interchange

OCTOBER 2020 UPDATE: RFP Process continues to progress toward submittal of bids by December 4, 2020 (adjusted from mid-November). Contract award remains on schedule for January 2021 with NTP to follow contract award by end of January 2021. Four separate a...

Read on...

Additional info... Projects
Posted on: November 13, 2020

Saturn Parkway Extension

Saturn Parkway

OCTOBER 2020 UPDATE: Roadway is open and final paving has been completed. The traffic signal has been energized and is operational. Punch list items are continuing to be addressed. According to a recent TDOT email, an official completion/close-out date ha...

Read on...

Additional Info... Projects
Posted on: November 5, 2020

U.S. 31 Widening Project

U.S. 31 Main Street through Spring Hill

OCTOBER 2020 UPDATE: TDOT has been having ongoing internal discussions regarding the absence of multi-modal opportunities within the R.O.W. There is a group within TDOT that would like to see sidewalks and bike lanes in the R.O.W. This position is balance...

Read on...

Projects
Posted on: January 4, 2017

Major Thoroughfare Plan

Major Thoroughfare Plan

The City of Spring Hill in July 2015 completed, and the BOMA approved, a Major Thoroughfare Plan, mapping out the long-term needs of Spring Hill's major roadways through 2040. It was done with insightful input through public meetings and social media.

Read on...

Projects