As part of the Duplex Road widening project, the following streets will be closed at their intersection with Duplex starting Monday, March 12, to allow for installation of new water and sewer lines:
- School Street – Between 9 a.m. and 3 p.m. for up to three days
- Walnut Street – Between 9 a.m. and 3 p.m. for up to three days
- Locke Avenue – Overnight and during the day for up to six days
These streets will close in sequence to minimize inconvenience. The opposite end of each street will remain open with signage indicating that temporarily no through traffic will be allowed. These are estimated times and will be “up to” the indicated days; each street may not take as long as indicated.